Transformers

Transformer 140 to Moorburg - Wedel



Transformer 140 to Moorburg - Wedel

In July 2009, we were responsible for moving a transformer from Moorburg power station to Wedel power station. The whole transport chain, from disassembly in Moorburg to installation onto foundations in Wedel, was organized by our company.




Installation onto foundations transformer 375 to Bad Essen



Installation onto foundations transformer 375 to Bad Essen

In June 2003, we were responsible for the installation of a 375-to-transformer in Bad Essen. Our scope of work started by unloading the railway wagon that was used for the main transport. Then, the transformer was transferred to the foundation site using the internal railways and then positioned using hydraulic jacking cylinders.